Arasar demolished over 30 linear metres of 450 mm thick reinforced-concrete road barrier for Wade Adams Contracting LLC in Deira during August 2026.
Project
Deira
Location
Deira, Dubai, UAE
Work type
Reinforced-concrete barrier removal
Related capability
Concrete cutting
Completed specialist work
The project in figures.
Client: Wade Adams Contracting LLC Project period: August 2026. Figures from Arasar's completed-project record.
Barrier length demolished
30+ m
Recorded barrier thickness
450 mm
30+ m means over 30 linear metres, not square metres or cubic metres. This reference concerns a road barrier, not demolition of surrounding buildings.
Equipment deployed on this package
Diamond sawing
Core drilling for lifting holes
Concrete separation
Diamond sawing separated the reinforced-concrete barrier into the required removal segments.
Lifting-hole drilling
Core holes were drilled to enable removal of the demolished segments.
Handling and relocation
The recorded package included organising handling and relocation of the demolished barrier sections.
Scope and constraint
The documented demolition package.
Scope. Diamond sawing of a reinforced-concrete road barrier, with core-drilled lifting holes and organised handling and relocation of the removed segments.
Constraint. The barrier was removed as individual concrete segments, requiring the cutting and lifting-hole work to be coordinated with handling and relocation.
Delivery. The reference records over 30 linear metres of barrier demolished, with a stated thickness of 450 mm. Handling and relocation of the demolished segments were organised within the package.
Reading the project evidence
What the project reference establishes.
The record identifies the delivered scope and its limits. It is not a generic capability claim or an illustrated reconstruction of the work.
Length and thickness distinguished
The reference states more than 30 linear metres and a barrier thickness of 450 mm. It does not state a removed concrete volume.
Lifting holes included
Core drilling provided lifting holes for the separated segments; the package was not described as saw cutting alone.
Segment handling
Handling and relocation are expressly included in the delivery record. No segment weight or off-site disposal destination is claimed.