Reinforced-concrete foundation removal · Sheikh Zayed Road, Dubai, UAE
Sheikh Zayed Road: reinforced-concrete foundation removal.
Arasar demolished 100 linear metres of 300–350 mm thick reinforced-concrete foundation for Wade Adams Contracting LLC on Sheikh Zayed Road in September 2026.
Arasar demolished 100 linear metres of 300–350 mm thick reinforced-concrete foundation for Wade Adams Contracting LLC on Sheikh Zayed Road in September 2026.
Project
Sheikh Zayed Road
Location
Sheikh Zayed Road, Dubai, UAE
Work type
Reinforced-concrete foundation removal
Related capability
Concrete foundation removal
Completed specialist work
The project in figures.
Client: Wade Adams Contracting LLC Project period: September 2026. Figures from Arasar's completed-project record.
Foundation length demolished
100 m
Recorded concrete thickness
300–350 mm
Length and thickness are reported separately. No volume, pile-head work, machine capacity or demolition of surrounding buildings is inferred from these measurements.
Equipment deployed on this package
Diamond sawing
Core drilling for lifting holes
Specified segmentation
The foundation slab was divided into the blocks required by the project's technical removal specification.
Sawing and lifting holes
Diamond sawing and core drilling prepared the foundation elements for subsequent handling.
Element removal
The recorded demolition package concerns the defined foundation slab, not demolition of Sheikh Zayed Road or nearby structures.
Scope and constraint
The documented demolition package.
Scope. Diamond sawing of a reinforced-concrete foundation slab, segmented for subsequent lifting and removal, including core drilling of lifting holes.
Constraint. The specified block segmentation connected the cutting work to subsequent lifting and removal of the demolished elements.
Delivery. The completed reference records 100 linear metres of reinforced-concrete foundation, 300–350 mm thick, demolished and lifting holes core-drilled for element removal.
Reading the project evidence
What the project reference establishes.
The record identifies the delivered scope and its limits. It is not a generic capability claim or an illustrated reconstruction of the work.
A defined foundation quantity
The documented quantity is 100 linear metres, with a thickness range of 300–350 mm. No width or total concrete volume is inferred.
Block segmentation
The sawing followed the specified segmentation requirements so the elements could subsequently be lifted and removed.
Separate from the Al Mustaqbal package
This September Sheikh Zayed Road reference is distinct from Arasar's July Al Mustaqbal Road foundation-cutting project. Their quantities are not combined.
Discuss a similar project
Plan your next structural alteration.
For foundation-slab removal, provide marked boundaries, length, width and thickness, retained reinforcement requirements and access for lifting equipment. Specify the removal depth and final cleared condition before pricing.